Attic or loft: the difference matters
The Code defines the two spaces differently (Annex no. 1). An attic (pod) is the space between the top floor slab and the roof, used for storage only. Over more than 75% of its area, either the clear height is below 1.90 m or there is no permanent access by a fixed staircase. An attic does not count as a floor of the building and is not included in the floor area ratio (CUT).
A loft (mansarda) is a functional space fitted out within the roof volume that meets the safety and comfort requirements for its use. The clear height of the areas considered usable is 1.90 m. Unlike an attic, a loft counts as a floor of the building, and its area is included in the floor area ratio.
The Code also contains a favourable rule: if fitting out an existing attic, without changing the roof geometry, leads to exceeding the floor area ratio permitted in the area, no zonal urban plan (PUZ) is required (Annex no. 1).
How it worked under Law no. 50/1991
Under Law no. 50/1991, turning an attic into living space was a modification of an existing building and required a building permit (article 3(1)(a)). It was not among the works exempt from authorisation (article 11). The law did, however, provide one facility: the permit could be issued without a prior urban plan, even if fitting out the attic exceeded the floor area ratio set for the area (article 11^1(b)).
The full procedure therefore involved a planning certificate, approvals, technical documentation and a building permit, issued within at most 30 days of filing the documentation (article 7(1)). Fitting out an attic without a permit was a minor offence punished with a fine of 1,000 to 100,000 lei (article 26(1)(a)).
What the Code now allows: notification
The Code introduces a simplified procedure, prior notification, for certain low-impact works. These include “works to fit out a loft in existing attics, including the provision of vertical circulation in single-family houses, without changes to the overall volume of the building, only if no strengthening measures for the building are required” (article 294(2)(b)(iii)).
Instead of a building permit, the owner informs the town hall before the works start, using a form accompanied by a simplified technical design. The notification has the value of a declaration on the owner’s own responsibility that the legal conditions are met (article 297(2)). In other words, the procedure is faster, but responsibility for classifying the works correctly lies with the owner and the designers.
The conditions, one by one
- Single-family house. The wording of the law refers to single-family houses. For other types of buildings, whether the procedure applies must be checked separately.
- Existing attic. The works concern an attic that already exists, not the creation of a new volume.
- No change to the overall volume. The external shape and dimensions of the building stay the same. Changing the shape of the roof to turn the attic into a loft, or to enlarge an existing loft, is called “mansardare” (article 372(2)(l)) and may only be done on the basis of a building permit (Annex no. 1).
- No strengthening works. If the structure of the house must be strengthened to carry the new loads, the notification procedure cannot be used. It is therefore advisable to have the structure assessed by a structural engineer before choosing the procedure.
- Outside protected areas. The house must not be in a protected built area or in the protection zone of a historic monument (article 294(2)(b)).
- Compliance with planning, quality and environmental rules. The works must comply with the planning regulations in force, construction quality standards and environmental impact legislation (article 294(2) and (5), article 297(3) and (6)).
Which documents are filed
- the notification form approved by ministerial order (article 295(10));
- the simplified technical design, prepared by an architect with signing rights and by engineers, each in their own field (article 295(4));
- any additional documentation required by law in specific cases (article 295(7));
- proof that the fees have been paid.
The notification is filed by the holder of a principal real right over the property, usually the owner, or, where applicable, by the holder of a contractual right (article 295(2)). It can be sent on paper or digitally, and the town hall confirms receipt (article 295(5) and (6)). The design does not need to be checked by certified technical reviewers, but responsibility for its correctness lies solely with the designers (article 298(2)).
How long it takes and when works can start
The town hall has 15 working days from receiving the notification (article 296(1)). Within this period, it may:
- not respond, in which case tacit approval applies when the period ends;
- ask for technical clarifications or for mandatory documents to be added;
- ask for additional documentation in order to obtain approvals and agreements;
- inform the owner that the works require a building or regularisation permit;
- reject the notification, with reasons, if the works breach the urban plans or other legal conditions.
Works may start 15 calendar days after the 15-working-day period ends or, if clarifications or documents were requested, after those requirements have been fully met (article 296(6) and article 298(1)). For a complete file, the time from filing to the start of works is therefore about five weeks. Notified works must be carried out within three years (article 296(5)).
Fees
For works carried out by notification, the fee charged by the town hall is half of the fee set by the Fiscal Code for a building permit (article 313(4) of the Code). For a residential building, the permit fee is 0.5% of the value of the works (article 474(5) of the Fiscal Code), so for a notification it is halved. The 0.1% state inspection levy for spatial planning and urbanism is also halved (article 143(4) and (5) of the Code).
During the works and at completion
- when works start, the project identification board must be displayed in a visible place (article 298(5));
- works may be carried out by a contractor or by the owner directly (article 298(4)), but always according to the notified design;
- at completion, acceptance takes place between the contractor, the owner and a town hall representative, and the acceptance report is registered in the National Construction Register; until the register is operational, a copy is sent to the State Construction Inspectorate (article 298(6));
- the loft can be entered in the land register on the basis of proof that the notification was filed and that its registration in the National Construction Register has been checked (article 298(7)).
Carrying out works without prior notification or in breach of the notified design is punished with a fine of 5,000 to 50,000 lei (article 357(1)(a) and (4)(a)). The inspection body orders, as the case may be, that the works be brought in line with the notified design, regularised or demolished (article 358(1)).
Attic conversions done without a permit before the Code
This is a common situation: the attic was turned into rooms before 25 August 2026 without a building permit. Under Law no. 50/1991, this was a minor offence, and the Code coming into force does not legalise it automatically.
No “retroactive” notification
A notification is always made before the works start (article 295(1)). The Code does not provide for a notification of works already carried out, even if, by their nature, they would fall within the simplified procedure today. For works carried out without a permit, the route provided by law is the regularisation permit (article 301), explained in detail in the article on houses built without a permit.
Which regularisation regime applies
The regime depends on the features of the house after the loft has been fitted out:
- if the house falls within the category in article 301(2), that is, a single-family house with a ground floor, or a ground floor and one upper floor, with a total floor area of up to 150 sq m, outside protected areas, regularisation can be requested at any time, at ordinary fees;
- in all other cases, regularisation can only be requested within one year of the Code coming into force, until August 2027, with fees and levies ten times higher (article 301(7) and (8)).
In both cases, regularisation involves checking planning rules and quality requirements through technical expert reports for each fundamental requirement. For a loft, the reports on structural strength and stability and on fire safety are usually particularly important.
Fines for works done before the Code
The Code’s much higher fines do not apply retroactively (article 15(2) of the Romanian Constitution). For works carried out under Law no. 50/1991, the fine was 1,000 to 100,000 lei, and the right to impose it lapsed three years after the offence (articles 26 and 31 of Law no. 50/1991). The lapse of the limitation period prevents the fine from being imposed, but does not legalise the works: the loft remains unauthorised until it is regularised. Each situation is assessed according to when the works were carried out and completed.
The increased building tax
The Code increases the building tax by 100% for buildings erected without a permit and not regularised (article 301(11)). It is not yet settled whether this increase also applies to a lawfully built house in which a loft was later fitted out without a permit. MDLPA Order no. 1389/2026, an interpretative act, concerns balcony enclosures only and states that the increase does not apply to a balcony enclosed in a lawfully built block of flats. The order’s reasoning may be relied on by analogy for lofts, but until there is an express clarification, the outcome is not certain.
How a lawyer can help
Before works start, the office can assess, together with the designer, whether the works fall within the notification procedure or require a building permit. For lofts already fitted out, the office can review the legal status of the property, the applicable regularisation regime and the minor-offence or tax risks. Details on the real estate law page.
Frequently asked questions
Do I need a building permit to convert my attic into a loft?
Not always. Since 25 August 2026, if the building is a single-family house, the attic already exists, the volume of the house does not change, no strengthening is needed and the house is not in a protected area, the works can be carried out by notification. If the shape of the roof is changed to create living space, a building permit is required.
What happens if the town hall does not respond to the notification?
If the town hall does not respond within 15 working days of receiving the notification, tacit approval applies. Works may start after a further 15 calendar days. It is important to keep proof of filing and of the registration date.
Can I raise the roof to gain more height in the loft?
The Code allows the roof to be replaced by notification in the same shape, or reshaped and raised by at most 0.50 m, within the maximum height allowed. A more extensive change to the roof shape is “mansardare” and requires a building permit. Combining the two types of works should be assessed by the designer together with the town hall.
I converted my attic without a permit a few years ago. Can I file a notification now?
No. A notification is only made before the works start. For works already carried out without a permit, the Code provides for the regularisation permit, which can be requested at any time or only until August 2027, depending on the features of the house.
Can a loft fitted out by notification be entered in the land register?
Yes. Under article 298(7) of the Code, land register entry is made on the basis of proof that the notification was filed and that its registration in the National Construction Register has been checked, after the works have been accepted.
Legal basis
This article is for information only and reflects the law in force at the date of publication. It does not constitute legal advice for any specific situation.