What changed on 25 August 2026
Law no. 169/2026 was published in the Official Gazette no. 661 of 10 August 2026 and has applied since 25 August 2026. From that date, Law no. 50/1991 on the authorisation of construction works is repealed, and the rules on permits, inspections and sanctions are found in the Code.
For works carried out without a building permit or in breach of one, the Code provides a separate procedure: the regularisation permit (article 301). It is requested from the authority that would have been competent to issue the building permit, usually the town hall where the property is located.
How it worked under Law no. 50/1991
Building a house without a permit was prohibited under the old law as well. Construction works could only be carried out on the basis of a building permit (article 1(1) of Law no. 50/1991), and a breach was a minor offence punished with a fine of 1,000 to 100,000 lei (article 26).
Together with the fine, the inspection body ordered the works to stop and set a deadline by which the owner had either to obtain the permit, the so-called “return to legality”, or to demolish the works (article 28). The right to impose the fine lapsed three years after the offence (article 31). After that period, the building could be entered in the land register on the basis of a certificate attesting its construction, issued on the strength of a technical expert report confirming compliance with quality requirements and planning rules (article 37(6)).
The Code does not carry this mechanism over. According to clarifications published by the Ministry of Development, Public Works and Administration (MDLPA), applications filed after 25 August 2026 for buildings erected without a permit follow the regularisation procedure in article 301, which starts with a planning certificate (certificat de urbanism) issued under the Code. Attestation certificates issued earlier under article 37(6) of Law no. 50/1991 remain valid for land register entry.
Which buildings can be regularised, and until when
The Code divides buildings into two categories. The difference is essential, because both the deadline and the costs depend on it.
Regularisation possible at any time
Under article 301(2), a regularisation permit can be issued, with no time limit, for:
- single-family houses with a ground floor, or a ground floor and one upper floor, with a total floor area of up to 150 sq m, which are not historic monuments and are not located in a monument protection zone or a protected built area;
- outbuildings of houses, household outbuildings or farm outbuildings with a total floor area of up to 150 sq m;
- balcony enclosures that do not extend over public land.
Total floor area is the sum of the areas of all floors, measured on the outside of the walls, not just the footprint of the house. A house with a ground floor and an upper floor of 80 sq m each therefore has around 160 sq m of total floor area and exceeds the threshold.
Regularisation possible for one year only
For any other building erected without a permit or in breach of one, such as a house larger than 150 sq m, a house with more floors or a building with another use, regularisation can only be requested within a period of at most one year after the Code came into force (article 301(7)), that is, until August 2027.
In this case, the law requires the works to comply with the planning regulations approved on the date the regularisation permit is issued and with the fundamental quality requirements for construction, and requires tax obligations to be met and minor-offence measures to have been applied.
Conditions the building must meet
Regularisation is neither a mere formality nor the automatic effect of paying a fee. The permit is issued only if all the conditions in article 301(3) and (4) are met:
- the building complies with the applicable planning rules, such as the permitted use of the area, distances from neighbours, maximum height and the land occupancy and floor area ratios;
- the building meets the fundamental quality requirements for construction set out in article 386 of the Code;
- environmental protection rules are complied with, as checked by the competent environmental authority;
- where relevant, special requirements for properties belonging to defence, public order and national security institutions are met.
If these conditions are not met, the authority applies the rules on demolition (article 301(5)). If there are technical solutions to bring the building into compliance, the town hall may require a building permit or partial demolition (paragraph 6), or may request works to bring the building into compliance (paragraph 10).
Which documents are required
The procedure has several stages, and each involves documents prepared by licensed specialists:
- The planning certificate (certificat de urbanism). It is requested from the town hall, and the Code expressly provides that it is also issued for the regularisation of a building. It is issued within at most 15 working days (article 257(4)). The certificate sets out the applicable planning rules and the approvals required.
- The approvals and agreements required by the planning certificate, including the environmental authority’s decision where applicable.
- Technical expert reports. Compliance with quality requirements is checked through reports by certified technical experts, one for each requirement: mechanical strength and stability, fire safety, hygiene, health and environment, safety and accessibility in use, noise protection, and energy saving and thermal insulation (article 301(9)).
- Planning compliance check. Compliance with planning rules is checked by the town hall’s specialist department or, if it lacks qualified staff, by an urban planning specialist with signing rights hired by the applicant (article 301(9)).
- The regularisation application, on the standard form approved by the ministry, together with the documentation and proof that the fees have been paid.
In practice, the file usually also includes documents proving rights over the land and the building, as well as cadastral documentation. The exact list follows from the planning certificate and may vary from one town hall to another.
The Code does not set a separate deadline for issuing the regularisation permit. For a building permit, the deadline is at most 30 calendar days after a complete file is filed (article 273(1)), and issuing a regularisation permit after the legal deadline is a minor offence (article 357(1)(l)). In reality, the length of the procedure depends mainly on the time needed for expert reports and approvals.
Fees and costs
The permit fee is calculated under the Romanian Fiscal Code (article 313(1) of the Code). For a residential building or an outbuilding, it is 0.5% of the value of the works (article 474(5) of the Fiscal Code), a value that cannot be lower than the taxable value of the building (article 474(7)(b)). In addition, there are state inspection levies of 0.1% (article 143(4) of the Code) and 0.5% payable to the State Construction Inspectorate (article 352(1)), as well as the architecture stamp duty under Law no. 35/1994.
The major difference arises under the one-year exceptional regime. For buildings regularised under article 301(7), the state inspection levies, the planning certificate fee and the permit fee are ten times higher than they would have been had the works been carried out lawfully (article 301(8)). According to MDLPA clarifications, this increase does not apply to the houses, outbuildings and balconies in the category that can be regularised at any time.
Besides fees, professional costs should be considered: technical expert reports, the planning compliance check, cadastral documentation and, where applicable, the cost of works needed to bring the building into compliance. The exact amount of the fees is set by the town hall under the Fiscal Code and local council decisions.
The Code also introduces a tax increase. For buildings erected without a permit that had not been regularised by the time the Code came into force, the building tax is increased by 100%, from the date the town hall establishes the situation until regularisation or demolition (article 301(11)). Paying the increased tax does not legalise the building and does not remove the sanctions.
Fines and other sanctions
For acts committed after 25 August 2026, the Code provides for much higher fines than the old law. Carrying out works without a building or regularisation permit, or in breach of one, is punished with a fine of 50,000 to 1,000,000 lei, depending on the seriousness of the act and its impact on neighbouring properties (article 357(1)(b) and (4)(b)). If the height limits in the permit are not complied with, an additional fine of 50,000 to 500,000 lei applies for each unauthorised floor (article 357(5)).
Fines may be imposed by the State Construction Inspectorate or by the inspection departments of local authorities (article 357(9)). Together with the fine, the inspection body orders the works to stop and, as the case may be, requires a regularisation permit to be obtained or the works to be demolished (article 358(1)). If the owner does not comply within the deadline set, the authority applies to the court (article 358(3)).
In certain situations the act is a criminal offence, for example building without a permit on a historic monument, in its protection zone or in a protected built area, or continuing works after they have been stopped by the inspection bodies (article 356).
Houses built before 25 August 2026
Under the Romanian Constitution, a law applies only for the future, except for a more favourable criminal or minor-offence law (article 15(2)). The Code’s higher fines therefore do not apply retroactively to acts committed before 25 August 2026. For such acts, the analysis is made case by case, depending on when the works were carried out and on the sanctions regime in force at that time.
One issue not yet settled is the limitation period for fines. Law no. 50/1991 provided for a three-year period, but the Code does not expressly set such a period for the offences in article 357 and excludes the application of Government Ordinance no. 2/2001 (article 581(3)). MDLPA Order no. 1389/2026, issued for balconies, refers to a general three-year period, but until there is a legislative clarification or consistent case law, this point should be treated with caution. In any event, the lapse of the limitation period does not legalise the building.
What happens after the deadline
Once the one-year period has expired, local authorities may demolish unauthorised works and recover the costs or, as the case may be, must ask the court to order the demolition of buildings that have not obtained a regularisation permit (article 301(12)). The mayor files the action within 30 days of the deadline, based on a finding report drawn up by the town hall or the State Construction Inspectorate (paragraph 13). The court may order total or partial demolition or restoration to the previous state, and the judgment is enforced at the offender’s expense (paragraphs 14 and 15).
Why it also matters when selling
An unlegalised building may cause difficulties with land register entry, with a sale or with obtaining a mortgage. Before buying a house, it is worth checking whether it was authorised and formally accepted on completion. See the article on the documents to check when buying a home. If the works concern an attic turned into living space, see also the article on converting an attic on the basis of a notification.
The office can review the legal status of the property and the existing documents, determine the category into which the building falls, and assist in dealings with the town hall, in minor-offence proceedings or before the court. Details on the real estate law page.
Frequently asked questions
Can I regularise a house built without a permit a few years ago?
Yes, if the conditions in article 301 of the Code are met. Houses with a ground floor, or a ground floor and one upper floor, of up to 150 sq m of total floor area, located outside protected areas, can be regularised at any time. For other buildings, the application must be filed within one year of the Code coming into force, until August 2027.
Do the tenfold fees apply to everyone?
No. Under article 301(8) and the MDLPA clarifications, the increase only concerns buildings regularised under the one-year exceptional regime, not the houses, outbuildings and balconies that can be regularised at any time.
Does paying the building tax legalise the building?
No. The Code expressly states that paying the tax, including the tax increased by 100%, has no effect on regularising the building and does not remove the sanctions.
Can I still obtain the attestation certificate provided by Law no. 50/1991?
New applications filed after 25 August 2026 follow the regularisation procedure in the Code. Attestation certificates issued before that date remain valid for land register entry.
Can the town hall refuse regularisation?
Yes, if the planning, quality and environmental conditions are not all met. Where technical solutions exist, the town hall may request works to bring the building into compliance, a building permit or partial demolition. A refusal can be challenged under the Administrative Litigation Law no. 554/2004.